Projects
Mumias 380 TCH Expansion Project
CLIENT: Mumias Sugar Co. Limited
LOCATION: Mumias, Kenya
TYPE OF CONTRACT: EPCM
Services Provided:
Bosch Projects were awarded the engineering and project management contract to expand the Mumias Sugar Factory to 380 TCH in August 2004.
Features:
The project commenced with a scope definition and a detailed cost estimate which was negotiated into a control budget.
Overall features of this project:
LOCATION: Mumias, Kenya
TYPE OF CONTRACT: EPCM
Services Provided:
- Scope Definition
- Cost Estimates
- Engineering and Design
- Project Management
- Procurement
- Construction Management
- Commissioning
- Operational Assistance
Bosch Projects were awarded the engineering and project management contract to expand the Mumias Sugar Factory to 380 TCH in August 2004.
Features:
The project commenced with a scope definition and a detailed cost estimate which was negotiated into a control budget.
Overall features of this project:
- New “A” centrifugal station and MCC
- New 4,000 m2 Kestner Evaporator
- Various new pump stations and existing pump station upgrades
- New 340 m3 Continuous Vertical Crystalliser
- New “C” Massecuite Reheater
- Dewatering mill upgrade
- New bulk sugar scale and upgrade to existing mixed juice scale
- Supply and installation of new SCADA system
- Associated electrical and controls system upgrades
Category: Sugar